Evaluate activity sequences for constructability.

integrated master scheduler

Verify schedule integrity and evaluate logic and float paths. Analyze schedules from A/E firms and General Contractors.Monitor schedule deviations and variances and assist in developing alternate methods for corrective action.Assess impacts to the critical path and near-critical activities and report to the project team.

#Integrated master scheduler update

Develop monitor and update integrated project plans, Baseline schedules, and Master schedules so that projects can be executed in the most efficient manner possible.

#Integrated master scheduler software

Analyze schedules submitted in various software packages, but primarily Primavera P6.

  • Produce detailed critical path network schedules for projects within a standard Work Breakdown Structure.
  • Utilize baseline tracking for Master Schedule, ensuring the baseline progress is tracked against this baseline. Highlighting the project critical path to appropriately direct the efforts of the project team.
  • Produce schedule in Primavera P6 format.
  • Analyze and process project change orders for schedule impacts.
  • Maintain record of scope changes, trends and variances that potentially affect schedule performance.
  • Prepare and provide schedule progress reports, trending charts and schedule analysis on a periodic basis.
  • With assistance from Project Field Engineers, provide 3 week Look Ahead schedule to coordinate ongoing manufacturing operations.
  • Review schedules with project team members on a regular basis to ensure that accurate and timely data is incorporated in the schedule.
  • Assure credibility of the information contained in the schedule.
  • integrated master scheduler

    Ensure that true logic is applied to schedules, adequate resource loading done, and that the schedules are regularly updated. Ongoing support of a large portfolio of project schedules to determine correct critical path is identified.Position Summary: Support schedule management for a portfolio projects We offer our US staff a competitive salary and comprehensive benefits package including Medical, Dental, Flexible Spending Account including Dependent Care, Life Insurance, Short Term Disability, Long Term Disability, 401K, and employer match, Paid Vacation Time, Paid Sick Time, and Paid Holidays. In the US, our staff provide services on client sites coast to coast with a focus in the Pharmaceutical / Bio-Tech, Data Center and Themed/Attraction industries. We are, at heart, a construction company with an aim to provide top level services to our clients in high tech and challenging industries. Worldwide our locations include the USA, Australia, China, India, and Southeast Asia. Cockram Construction, founded in 1861, is an international construction services business, headquartered in Melbourne, Australia.